(058)
Building Employees Mixed
Industries (State) Award
INDUSTRIAL RELATIONS
COMMISSION OF NEW SOUTH WALES
Application by Construction,
Forestry, Mining and Energy Union (New South Wales Branch) , Industrial
Organisation of Employees.
(No. IRC 1883 of 2008)
Before Commissioner
Tabbaa
|
16 October 2008
|
VARIATION
1. Delete Part B,
Monetary Rates, of the award published 16 November 2001 (329 I.G. 577), and
insert in lieu thereof the following:
Part B
MONETARY RATES
Table 1 -Wages
|
Base
Rate
|
Supplementary
|
SWC
|
Tool
|
Ordinary
|
|
|
Payment
|
Adjustments
|
Allowance
|
Weekly
Rate
|
|
$
|
$
|
$
|
$
|
$
|
Carpenters & Joiners
|
367.30
|
38.20
|
215.40
|
25.80
|
646.70
|
Bricklayers
|
367.30
|
38.20
|
213.30
|
18.30
|
637.10
|
Plumbers including:
|
369.60
|
38.00
|
215.50
|
25.80
|
n/a
|
Gasfitters &
|
|
|
|
|
|
Drainers
|
|
|
|
|
|
Painters, Including:
|
367.30
|
38.00
|
215.40
|
6.20
|
n/a
|
Signwriters
|
|
|
|
|
|
Marblers, Grainers
|
|
|
|
|
|
& Artworkers
|
|
|
|
|
|
Builders Labourer
Classification
|
Previous
Ordinary
|
SWC
|
Current
Ordinary
|
|
Weekly
Rate
|
Adjustments
|
Weekly
Rate
|
|
$
|
$
|
$
|
1.
|
Rigger, Dogger
|
431.40
|
146.20
|
577.10
|
2.
|
Scaffolder (as defined), powder
|
420.20
|
145.80
|
566.00
|
monkey hoist or winch driver, foundation
|
|
|
|
shaftperson (as defined), concrete finisher
|
|
|
|
(as defined), steel fixer including tack
|
|
|
|
welder
|
|
|
|
3.
|
Bricklayer’s labourer, plasterer’s
|
408.00
|
145.30
|
553.30
|
labourer, assistant rigger (as defined),
|
|
|
|
assistant powder monkey (as defined)
|
|
|
|
demolition work (after 3 months experience)
|
|
|
|
gear hand, pile driver (concrete),
|
|
|
|
hammerperson, mixer driver (concrete), steel
|
|
|
|
erector, aluminium alloy structural erectors,
|
|
|
|
(whether pre-fabricated or otherwise), gantry
|
|
|
|
hand or crane hand, crane chaser, cement
|
|
|
|
gun operator, concrete cutting or drilling
|
|
|
|
machine operator, concrete gang including
|
|
|
|
concrete floater (as defined), roof layer
|
|
|
|
(malthoid or similar material) dump cart
|
|
|
|
operator, under pinner, steel or bar bender to
|
|
|
|
pattern or plan, concrete formwork stripper
|
|
|
|
4.
|
Builder’s labourer employed on work
|
384.20
|
168.50
|
552.70
|
other than that specified in (1) to (3) hereof
|
|
|
|
Apprentices
Carpenters/Joiners/Bricklayers/Painters
|
Indentured
|
Trainees
|
|
$
|
$
|
1st Year
|
217.00
|
243.50
|
2nd Year
|
317.40
|
356.30
|
3rd Year
|
420.30
|
461.90
|
4th Year
|
491.50
|
518.80
|
Plumbers
|
$
|
$
|
1st Year
|
219.10
|
247.50
|
2nd Year
|
320.20
|
359.90
|
3rd Year
|
421.80
|
465.60
|
4th Year
|
496.10
|
523.80
|
Table 2 -
Allowances
Item
|
Clause
|
Description
|
Amount
|
|
|
|
$
|
|
|
Tool Allowance
|
|
1
|
16.1
|
Carpenter/Joiner
|
25.80 per week
|
|
16.1
|
Bricklayer
|
18.30 per week
|
|
16.2
|
Plumber
|
25.80 per week
|
|
16.3
|
Painter
|
6.20 per week
|
|
16.4
|
Plumber - Registration Allowance
|
0.50 per hour
|
2
|
|
Adjustments
|
|
|
16.2.2
|
Ships Plumber
|
0.28 per hour
|
|
16.2.3
|
Drainer (amount to be deducted)
|
0.05 per hour
|
|
16.3.2
|
Signwriter
|
0.45 per hour
|
|
16.3.3
|
Marbler and Grainer
|
0.45 per hour
|
|
16.3.4
|
Ship Painter
|
0.35 per hour
|
|
16.3.5
|
Casual Ships Painter
|
13.99 per day
|
|
16.3.6
|
Signwriter, Grainer, Gilder on Ship work
|
0.77 per hour
|
|
16.3.7(a)
|
Artworker Grade 2
|
0.44 per hour
|
|
16.3.7(b)
|
Artworker Grade 1
|
0.79 per hour
|
All Employees
|
3
|
17.2.1
|
Insulation
|
0.69 per hour
|
4
|
17.2.2
|
Hot Work
|
|
|
|
between 46 and 54 degrees
|
0.55 per hour
|
|
|
exceeding 54 degrees
|
0.69 per hour
|
5
|
17.2.3
|
Cold Work
|
0.55 per hour
|
6
|
17.2.4
|
Confined Spaces
|
0.69 per hour
|
7
|
17.2.5
|
Swing Scaffold
|
|
|
|
first four hours
|
3.99
|
|
|
every hour after
|
0.78 per hour
|
8
|
17.2.6
|
Wet Work
|
0.55 per hour
|
9
|
17.2.7
|
Dirty Work
|
0.55 per hour
|
10
|
17.2.8
|
Towers Allowance
|
|
|
|
above 15 meters in height
|
0.55 per hour
|
|
|
each additional 15 meters
|
0.55 per hour
|
11
|
17.2.9
|
Toxic Substances
|
|
|
|
preparation and application
|
0.69 per hour
|
|
|
when air conditioning plant not operating
|
0.45 per hour
|
|
|
Close Proximity to employees so engaged
|
0.55 per hour
|
12
|
17.2.11
|
Computing Quantities
|
|
|
|
All Trades except Plumbers
|
3.99 per day
|
|
|
Plumbers
|
0.55 per hour
|
13
|
17.2.12
|
Asbestos Eradication
|
1.85 per hour
|
Carpenters, Joiners and Bricklayers Only
|
14
|
17.3.1
|
Roof Work
|
0.69 per hour
|
15
|
17.3.2
|
Ship Repair
|
13.42 per week
|
16
|
17.3.3
|
Second Hand Timber
|
2.17 per day
|
17
|
17.3.4
|
Acid Work
|
1.46 per hour
|
18
|
17.3.5
|
Cleaning Down Brick Work
|
0.50 per hour
|
19
|
17.3.6
|
Bagging
|
0.50 per hour
|
20
|
17.3.7
|
Brick Cutting Machine
|
0.69 per hour
|
21
|
17.3.8
|
Heavy Blocks
|
|
|
|
weighting over 5.5 kg and under 9 kg
|
0.55 per hour
|
|
|
weighting over 9 kg and under 18 kg
|
1.01per hour
|
|
|
weighting over 18 kg
|
1.40 per hour
|
Carpenters, Joiners, Bricklayers and Painters
|
22
|
17.4.1
|
Tunnel and Shaft
|
0.69 per hour
|
23
|
17.4.2
|
Furnace Work
|
1.46 per hour
|
24
|
17.4.3
|
Explosive Power Tools
|
1.31 per hour
|
Plumbers Only
|
25
|
17.5.1
|
Chokages
|
6.28 per day
|
26
|
17.5.2
|
WC's Urinals
|
0.69 per hour
|
27
|
17.5.3
|
Height Work
|
0.55 per hour
|
28
|
17.5.4
|
Lead Burner
|
0.70 per hour
|
|
|
Lead Burner in Chemical Works
|
0.92 per hour
|
|
|
Oxyacetelyne or Electric Welding Certificate
|
0.50 per hour
|
|
|
Welding in Compliance with AS4041-1998
|
0.73 per hour
|
|
|
|
Min per day $5.60
|
|
|
Welding other then under 17.5.4(c)
|
0.12 per hour
|
29
|
17.5.5
|
Using or in close proximity to Asbestos
|
0.69 per hour
|
30
|
17.5.6
|
Slaughter Yards
|
1.31 per hour
|
31
|
17.5.7
|
Roof Work
|
0.77 per hour
|
32
|
17.5.8
|
Use of Licences
|
|
|
|
Plumber’s Licence
|
0.84 per hour
|
|
|
Gasfitter’s Licence
|
0.84 per hour
|
|
|
Drainer’s Licence
|
0.74 per hour
|
|
|
Plumber’s and Drainer’s Licence
|
1.13 per hour
|
|
|
Plumber’s and Gasfitter’s Licence
|
1.13 per hour
|
|
|
Gasfitter and Drainers Licence
|
1.58 per hour
|
33
|
17.5.9
|
District Allowance
|
|
|
(a)
|
|
0.89 per hour
|
|
(b)
|
|
1.46 per hour
|
|
(c)
|
|
1.46 per hour
|
Ship Plumbers
|
34
|
17.6.1
|
Ballast and Oil Tanks
|
0.69 per hour
|
34
|
17.6.2
|
Bilges
|
0.50 per hour
|
38
|
17.6.3
|
Diesel Engines
|
0.50 per hour
|
Painters
|
37
|
17.7.2
|
Height Work
|
0.50 per hour
|
38
|
17.7.3
|
Use of Rigging or Scaffold Certificate
|
0.55 per hour
|
39
|
17.7.4
|
Spray Allowance
|
0.55 per hour
|
40
|
17.7.5
|
Power Tools
|
0.55 per hour
|
Builders Labourers
|
41
|
16.4.2
|
Builders Labourer engaged on maintenance
|
14.53 per week
|
|
16.4.3
|
Builders Labourer other than on maintenance
|
9.73 per week
|
42
|
17.8.1
|
Work on Acid Resistant Brick Work
|
0.52 per hour
|
|
17.8.2
|
Boilers, furnaces, Kilns, etc
|
0.52 per hour
|
43
|
17.9.1
|
Apprentices use of Rigging or Scaffold Certificate
|
0.55 per hour
|
44
|
18
|
Leading Hand
|
Per week
|
|
|
Carpenters and Bricklayers
|
|
|
|
In charge of:
|
|
|
|
not more than 1 person
|
15.70 week
|
|
|
more than 2 but not more than 5 persons
|
34.40 week
|
|
|
more than 5 but not more than 10 persons
|
43.90 week
|
|
|
more than 10 persons
|
58.60 week
|
|
|
|
|
|
|
Plumbers
|
|
|
|
In charge of:
|
|
|
|
up to 2 journeypersons
|
0.75 per hour
|
|
|
3 to 5 journey persons
|
0.88 per hour
|
|
|
5 to 10 journeypersons
|
1.13 per hour
|
|
|
over 10 journeypersons
|
1.46 per hour
|
|
|
|
|
|
|
Painters
|
|
|
|
In charge of:
|
|
|
|
1 to 5 journeypersons (and/or apprentices)
|
6.91 per day
|
|
|
6 to 15 journeypersons (and/or apprentices)
|
8.61 per day
|
|
|
more than 15 journeypersons (and/or apprentices)
|
11.77 per day
|
|
|
|
|
|
|
Builders’ Labourers
|
|
|
|
In charge of
|
|
|
|
not less than 2 nor more than 5 persons
|
28.50 per week
|
|
|
not less than 5 nor more than 10 persons
|
35.70 per week
|
|
|
more than 10 persons
|
48.20 per week
|
45
|
20.3.2
|
Ships Work - Special Places
|
0.50 per hour
|
46
|
20.3.3
|
Insulations with granulated cork
|
0.50 per hour
|
47
|
20.4
|
Removal Bitumous Compounds
|
0.50 per hour
|
48
|
|
Industry Allowance
|
24.40 per week
|
49
|
15.2
|
Overtime Meal Allowance
|
11.90 per meal
|
50
|
22.3.1(b)
|
Living Away from Home - Weekly
|
398.40 per week
|
51
|
22.3.1(c)
|
Living Away from Home - Daily
|
57.00
per day
|
52
|
22.4.1(a)(iii)
|
Travel Expenses - Meal
|
11.90 per meal
|
|
22.4.1(b)(i)
|
Return Journey
|
19.70 per occasion
|
54
|
22.6.5
|
Weekend Return Home
|
33.40 per occasion
|
55
|
24.1.1
|
First Aid Allowance
|
2.28 per day
|
56
|
26.2.1
|
Loss of Tools and Clothing
|
1495.00
|
2. This variation
shall take effect from the beginning of the first pay period to commence on or
after 16 October 2008.
I.
TABBAA, Commissioner
____________________
Printed by